Ongoing Projects
Ghana MTA Staff Apartments Project, Bustane-Ahmad
AMJ International Grant Funded Construction Projects
Project Name: Ghana MTA Staff Apartments Project, Bustane-Ahmad
Location: Bustane-Ahmad, Accra, Ghana
Commenced: 31st May 2021
1_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
Site mobilisation and setting out work complete. Excavation work in progress.2_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
Substructure masonry blockwork in progress: Pad and strip foundation work complete3_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
Substructure work complete. Ground floor slab concrete pour complete.4_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
Ground floor RCC column work and masonry block work in progress.5_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
Ground floor masonry blockwork complete. First floor RCC slab form work steel assembly in
progress.6_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
First Floor RCC slab concrete pour complete.
Philippines Central Mosque Construction Project
AMJ International Grant Funded Construction Projects
Project Name: Philippines Central Mosque Construction Project
Location: Zamboanga, Philippines
Commenced: 17th February 2021
1_AMJ Philippines_Central Mosque Construction Project_Zamboanga
Site mobilisation and setting out work complete. Excavation and substructure work in progress.2_AMJ Philippines_Central Mosque Construction Project_Zamboanga
Substructure work complete. Ground floor RCC column work in progress.3_AMJ Philippines_Central Mosque Construction Project_Zamboanga
Ground floor RCC column work complete. RCC beam and roof slab steel assembly work in
progress.4_AMJ Philippines_Central Mosque Construction Project_Zamboanga
RCC roof slab concrete pour complete. Masonry block work in progress.5_AMJ Philippines_Central Mosque Construction Project_Zamboanga
Masonry blockwork complete.
Chad Central Mosque & Mission Construction Project
AMJ International Grant Funded Construction Projects
Project Name: Chad Central Mosque & Mission Construction Project
Location: N’Djamena, Chad
Commenced: 16th September 2020
1_AMJ Chad_Central Mosque and Mission Construction Project
Site mobilisation and setting out work commences2_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building substructure work complete3_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building masonry blockwork in progress.4_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building masonry blockwork reached first floor level5_AMJ Chad_Central Mosque and Mission Construction Project
Missionary residence substructure work complete6_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building cement plasterwork in progress7_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building interior paintwork and first-fix electrical work in progress.8_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building phase 1 complete. View of main façade.9_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building phase 1 complete. View of side façade10_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building phase 1 complete. Interior view of prayer hall.11_AMJ Chad_Central Mosque and Mission Construction Project
Missionary residence masonry blockwork in progress.12_AMJ Chad_Central Mosque and Mission Construction Project
Missionary residence masonry blockwork reaches roof level.13_AMJ Chad_Central Mosque and Mission Construction Project
Missionary residence rib & block roof slab concrete pour complete.
AMJ India, Continuous Development of Various Properties and sites, Progress through the year 2016
AMJ International Grant Funded Construction Projects
Project Name: AMJ India, Continuous Development of Various Properties and sites, Progress through the year 2016
Location: Various locations in India
Commenced: Continuous Development
1_AMJ India_Continuous Various Development
Construction of two flats, Mohallah Akalgarh, Qadian.2_AMJ India_Continuous Various Development
Construction of two flats, Interior, Mohallah Akalgarh, Qadian.3_AMJ India_Continuous Various Development
Construction of WC facilities, front view, Bahishti Maqbarah Cemetery, Qadian.4_AMJ India_Continuous Various Development
Construction of four flats, exterior view, Mohallah Ahmadiyya, Qadian.5_AMJ India_Continuous Various Development
Construction of four flats, typical interior, Mohallah Ahmadiyya, Qadian.6_AMJ India_Continuous Various Development
Construction of Khilafat Jubilee Monument, Bahishti Maqbarah Cemetery, Qadian.7_AMJ India_Continuous Various Development
Construction of Khilafat Jubilee Monument, night view, Bahishti Maqbarah Cemetery, Qadian.8_AMJ India_Continuous Various Development
Exterior lighting upgrade, Khilafat Jubilee Monument, Bahishti Maqbarah Cemetery, Qadian.9_AMJ India_Continuous Various Development
Pathway paving upgrade, Bahishti Maqbarah Cemetery, Qadian.10_AMJ India_Continuous Various Development
Renovation and Restoration of Masjid (Mosque) Aqsa New Portion, Qadian.11_AMJ India_Continuous Various Development
Renovation and Restoration of Masjid (Mosque) Aqsa Old Portion, Qadian.12_AMJ India_Continuous Various Development
Block 4 Construction, Six Flats, Kothi Darul Salam, Qadian.13_AMJ India_Continuous Various Development
Renovation of Taleem-ul-Islam High School Building, Qadian.14_AMJ India_Continuous Various Development
Renovation of Darul Bait Building, Ludhiana.15_AMJ India_Continuous Various Development
New-build Construction, Taleem-ul-Islam School Building, Qadian.16_AMJ India_Continuous Various Development
New Road Construction, Jalsa Gah Ground, Qadian.17_AMJ India_Continuous Various Development
New Road Construction, Jalsa Gah Ground, Qadian.18_AMJ India_Continuous Various Development
New-build Construction, Darul Ziafat Building, Qadian.19_AMJ India_Continuous Various Development
New-build Construction, Darul Ziafat Building, Qadian. External plasterwork and paintwork.20_AMJ India_Continuous Various Development
New-build Construction, Darul Ziafat Building, Qadian. External finishing work.21_AMJ India_Continuous Various Development
Renovation of Langar Khana (catering kitchen facility) No.1, Qadian.22_AMJ India_Continuous Various Development
Renovation of Langar Khana (catering kitchen facility) No.3, Qadian. External plasterwork.23_AMJ India_Continuous Various Development
Renovation of Langar Khana (catering kitchen facility) No.3, Qadian. Front view.24_AMJ India_Continuous Various Development
Renovation of Publications Warehouse (Nashro Ishaat), Qadian.25_AMJ India_Continuous Various Development
Marble restoration of the tomb of Hadhrat Mirza Ghulam Murtaza Sahib (rh)26_AMJ India_Continuous Various Development
New-build Construction, Police Quarters near Bahishti Maqbarah Cemetery, Qadian.27_AMJ India_Continuous Various Development
New-build Construction, Police Quarters near Darul Masih, Qadian.28_AMJ India_Continuous Various Development
Renovation of four storey block, Mohalla Ahmadiyya, Qadian.29_AMJ India_Continuous Various Development
New-build Construction, Darul Sanaat, Qadian. Exterior View.30_AMJ India_Continuous Various Development
New-build Construction, Darul Sanaat, Qadian. Interior.31_AMJ India_Continuous Various Development
Construction of WC facilities, Jalsa Gah, Qadian. Internal partition work.32_AMJ India_Continuous Various Development
Construction of WC facilities, Jalsa Gah, Qadian. Completed interior.
Finished Projects
Belize Central Mosque & Mission Construction Project
AMJ International Grant Funded Construction Projects
Project Name: Belize Central Mosque & Mission Construction Project
Location: Belize City, Belize
Commenced: 14th December 2019
Completed: 20th May 2021
1_AMJ Belize_Mosque and Mission Construction Project
Demolition of existing building and clearing land.2_AMJ Belize_Mosque and Mission Construction Project
Demolition of existing building complete.3_AMJ Belize_Mosque and Mission Construction Project
Foundation work commenced. Precast reinforced concrete piles driven into the ground4_AMJ Belize_Mosque and Mission Construction Project
Tie-beam and pile-caps form work and casting in progress.5_AMJ Belize_Mosque and Mission Construction Project
Tie-beam and pile-caps casting complete. Masonry block work in progress.6_AMJ Belize_Mosque and Mission Construction Project
Sub-structure work complete. Masonry block work reached plinth level.Project1_Belize_Mosque_Mission – 3D View – 3D View 1
3D ViewElevation
7_AMJ Belize_Mosque and Mission Construction Project
Masonry block work in progress.8_AMJ Belize_Mosque and Mission Construction Project
Masonry block work reaches first floor level.9_AMJ Belize_Mosque and Mission Construction Project
Masonry block work complete. Roof slab concrete pour in progress.10_AMJ Belize_Mosque and Mission Construction Project
Superstructure complete. External ornamentation work in progress.11_AMJ Belize_Mosque and Mission Construction Project
External paintwork in progress. Dome and minarets installed.12_AMJ Belize_Mosque and Mission Construction Project
Mosque building complete. View from front façade.13_AMJ Belize_Mosque and Mission Construction Project
Mosque building complete. View from rear façade.14_AMJ Belize_Mosque and Mission Construction Project
Mosque building complete. Interior view of prayer hall.15_AMJ Belize_Mosque and Mission Construction Project
Mosque building complete. View from main road.
Macedonia New Mission Construction Project
AMJ International Grant Funded Construction Projects
Project Name: Macedonia New Mission Construction Project
Location: Pehchevo, Macedonia
Commenced: 20th February 2019
Status: Completed 30th October 2020
1_AMJ Macedonia_New Mission Construction Project
Jama`at land before construction.2_AMJ Macedonia_New Mission Construction Project
Foundation trenches excavated.3_AMJ Macedonia_New Mission Construction Project
Foundation concrete poured, reinforced concrete steal columns assembled and concrete cast up to first floor.4_AMJ Macedonia_New Mission Construction Project
Reinforced concrete structure work carried out to second floor.5_AMJ Macedonia_New Mission Construction Project
Reinforced concrete structure work carried out to roof level. External masonry block work is completed. Roof work is completed.6_AMJ Macedonia_New Mission Construction Project
Internal masonry block and first-fix electrical work complete.7_AMJ Macedonia_New Mission Construction Project
Internal plasterwork complete and windows fitted.8_AMJ Macedonia_New Mission Construction Project
Interior finishes work commences.9_AMJ Macedonia_New Mission Construction Project
Interior fixtures and fittings work in progress.10_AMJ Macedonia_New Mission Construction Project
All windows and doors fitted.11_AMJ Macedonia_New Mission Construction Project
Landscaping work commenced. Retaining wall construction in progress.12_AMJ Macedonia_New Mission Construction Project
Rear terrace retaining wall construction in progress.13_AMJ Macedonia_New Mission Construction Project
Building façade work in progress. Rear terrace retaining wall constructed.14_AMJ Macedonia_New Mission Construction Project
Building façade render work is complete.15_AMJ Macedonia_New Mission Construction Project
Principle view of finished building16_AMJ Macedonia_New Mission Construction Project
Rear view of finished building.17_AMJ Macedonia_New Mission Construction Project
Night time rear view of finished building.18_AMJ Macedonia_New Mission Construction Project
Principle façade entrance detail finished.19_AMJ Macedonia_New Mission Construction Project
Completed window pane details.20_AMJ Macedonia_New Mission Construction Project
Finished interior view of prayer area.
Guatemala Local Mosque & Mission Construction Project
AMJ International Grant Funded Construction Projects
Project Name: Guatemala Local Mosque & Mission Construction Project
Location: Cahabon, Guatemala
Commenced: 10th December 2019
Status: Completed 30th July 2020
1_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Site levelled and foundation trenches excavated.2_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Strip foundation concrete poured and plinth beam work in progress.3_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Ground floor masonry blockwork in progress.4_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
First floor reinforced concrete floor slab constructed. Frist floor masonry blockwork in progress.5_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Frist floor masonry blockwork reached roof level.6_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Reinforced concrete roof slab work complete.7_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Interior surface finishes and fixtures work progress.8_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
External plasterwork, minaret and site boundary wall construction in progress.9_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Minaret construction complete. White cement plaster work in progress10_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Principle view of completed mosque from road.11_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
View of completed mosque from rear.12_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Minaret with scenic backdrop13_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Finished main prayer hall interior.14_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Finished main prayer hall interior.
MSAF Islamabad Development Project. Phase 2: Residential Blocks
AMJ International Grant Funded Construction Projects
Project Name: MSAF Islamabad Development Project. Phase 2: Residential Blocks
Location: Tilford, Surrey, UK
Commenced: September 2017
Completed: April 2019
1_AMJ MSAF_Islamabad Development Project_Phase2
Demolition of existing buildings and clearing land.2_AMJ MSAF_Islamabad Development Project_Phase2
Land cleared.3_AMJ MSAF_Islamabad Development Project_Phase2
Foundation trenches excavated and strip foundation concrete being poured.4_AMJ MSAF_Islamabad Development Project_Phase2
Block 8 foundation work complete, ground floor block and beam floor work in progress.5_AMJ MSAF_Islamabad Development Project_Phase2
Masonry blockwork in progress.6_AMJ MSAF_Islamabad Development Project_Phase2
Masonry blockwork reaches first floor level. Floor joist work in progress.7_AMJ MSAF_Islamabad Development Project_Phase2
Masonry blockwork complete. Timber frame roof work in progress.8_AMJ MSAF_Islamabad Development Project_Phase2
Roof tile work in progress after installation of roof insulation and breather membrane.9_AMJ MSAF_Islamabad Development Project_Phase2
Building clad with composite panels resembling cedar wood.10_AMJ MSAF_Islamabad Development Project_Phase2
Completed residential blocks.
MSAF Islamabad Development Project. Phase 1: Mosque, Multi-Purpose Hall, Mix-use and Residential Blocks
AMJ International Grant Funded Construction Projects
Project Name: MSAF Islamabad Development Project. Phase 1: Mosque, Multi-Purpose Hall, Mix-use and Residential Blocks
Location: Tilford, Surrey, UK
Commenced: 24th October 2016
Completed: April 2019
1_AMJ MSAF_Islamabad Development Project_Phase1
Demolition of existing and clearing land.2_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall foundation work following excavation and land clearance work.3_AMJ MSAF_Islamabad Development Project_Phase1
Mosque foundation trench excavated and foundation stone set.4_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall foundation work. Concrete being poured for slab.5_AMJ MSAF_Islamabad Development Project_Phase1
Mosque foundation work. Concrete being poured for slab.6_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall steal erected. Mosque prep-work for reinforced concrete wall concrete pour.7_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block foundations trench excavated and concrete poured.8_AMJ MSAF_Islamabad Development Project_Phase1
Mosque reinforced concrete wall complete. Multi-purpose hall roof decking work in progress.9_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall roof decking complete. Super-structure masonry blockwork in progress.10_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ground floor slab concrete work pour complete, masonry brick-work in progress.11_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall brick veneer, breather membrane and roof substrate(organic and non-organic
material) work in progress.12_AMJ MSAF_Islamabad Development Project_Phase1
Mosque roof steelwork complete and installation of first GRP copper finish over timber
decking/sheathing and dampproof membrane.13_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘S’ beam and block floor work in-progress and steal portal frame assembled.14_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘1’ breather membrane installation after timber stud wall and timber roof joist
work complete.15_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall interior plaster skimming work, plant room installations, first-fix M&E work and
installation if windows.16_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘S’ external masonry leaf complete, interior masonry blockwork and timber roof
joist work in progress.17_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘1’ installation of slate roof tiles.18_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall first-fix MEP work in progress.19_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall first-fix MEP work, interior plasterwork, dampproof membrane and underfloor heating work in-progress.20_AMJ MSAF_Islamabad Development Project_Phase1
Mosque GRP copper finish panel installation continues.21_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Blocks first-fix MEP work along with the preparation of interior stud walls.22_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall first-fix MEP work continues.23_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall external timber cladding work commences.24_AMJ MSAF_Islamabad Development Project_Phase1
Mosque temporary interior steel work removed and first fix MEP work commences.25_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘1’ installation of external timber cladding.26_AMJ MSAF_Islamabad Development Project_Phase1
Mosque dome fixed in place.27_AMJ MSAF_Islamabad Development Project_Phase1
Mosque interior plasterboards installed following insulation and first-fix electrical installation.28_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall lighting installed and screeding complete.29_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall bathroom fixtures and finishing work in progress.30_AMJ MSAF_Islamabad Development Project_Phase1
Mosque dome pinnacle ornament fixed in place.31_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall hard landscaping work commences.32_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Blocks hard landscaping work commences.33_AMJ MSAF_Islamabad Development Project_Phase1
Mosque internal plasterwork continues.34_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Blocks interior finishing and light fixtures work in progress.35_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block 6 complete36_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘S’ complete37_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block 1 complete38_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall exterior view, complete39_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall interior, complete40_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall washroom facilitates complete41_AMJ MSAF_Islamabad Development Project_Phase1
Mosque exterior view, complete42_AMJ MSAF_Islamabad Development Project_Phase1
Mosque interior view, complete
Archived Projects
AMJ Mali Central Mosque and Mission Project
AMJ International Grant Funded Construction Projects
Project Name: AMJ Mali Central Mosque and Mission Project
Location: Bamako, Mali
Commenced: March 2017
Completed: 2018
1_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mosque ground floor slab steel re-bar assembly in progress following completion of excavation and substructure work2_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mosque ground floor slab concrete pour complete.3_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Admin building substructure, ground floor structure and ground floor blockwork complete. First floor blockwork in progress.4_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mission building first floor reinforced concrete column and beam structure casting in progress.5_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mosque ground floor blockwork complete. Columns and beams concrete pour in progress.6_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mission building first floor structure work complete.7_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mission building superstructure work complete.8_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Prayer area plasterwork and first-fix works in progress.9_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mosque structural work complete up to first floor.10_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mosque building superstructure work complete and minaret preparation in progress.11_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Completed prayer area.12_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Completed Mosque building.13_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Completed Mosque and Jamaat Mission building
Jamia Ahmadiyya International, Student Hostels, Ghana
AMJ International Grant Funded Construction Projects
Project Name: Jamia Ahmadiyya International, Student Hostels
Location: Jamia Ahmadiyya International, Mankessim, Ghana
Commenced: 29th June 2015
Completed: 25th June 2016
1_AMJ Ghana_Jamia Student Hostel
Over 3000 sqm of land cleared. Building profile marked out. Foundation trenches excavated.2_AMJ Ghana_Jamia Student Hostel
Steel reinforcement pads and columns starters were placed. Foundation concrete was poured.3_AMJ Ghana_Jamia Student Hostel
Blocks were laid to up to plinth level.4_AMJ Ghana_Jamia Student Hostel
Excavation was back-filled. Super-structure work commenced.5_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ works6_AMJ Ghana_Jamia Student Hostel
Columns were cast and masonry block were laid up to roof level.7_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ works8_AMJ Ghana_Jamia Student Hostel
Casting of ‘Hostel A’ beam.9_AMJ Ghana_Jamia Student Hostel
Sanitary drainage pipes were laid for washrooms.10_AMJ Ghana_Jamia Student Hostel
Student Washrooms super-structure work and interior partition work commenced11_AMJ Ghana_Jamia Student Hostel
‘Hostel B’ works12_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ all columns and beams were cast and block-work finished up-to roof level.13_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ interior works.14_AMJ Ghana_Jamia Student Hostel
‘Hostel B’ works.15_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ timber frame roof works commenced.16_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ timber frame roof works.17_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ timber frame roof works.18_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ timber frame roof works.19_AMJ Ghana_Jamia Student Hostel
20_AMJ Ghana_Jamia Student Hostel
Timber frame roof works Complete.21_AMJ Ghana_Jamia Student Hostel
Timber frame roof works Complete.22_AMJ Ghana_Jamia Student Hostel
Roofing metal sheets fixed.23_AMJ Ghana_Jamia Student Hostel
Roofing metal sheets fixed.24_AMJ Ghana_Jamia Student Hostel
Roofing metal sheet work complete. Damp-proof applied.25_AMJ Ghana_Jamia Student Hostel
Fine cement plaster work in progress with doors/window frames being fixed.26_AMJ Ghana_Jamia Student Hostel
Exterior plaster work in progress with doors/window frames being fixed.27_AMJ Ghana_Jamia Student Hostel
Exterior plaster work in progress with doors/window frames being fixed.28_AMJ Ghana_Jamia Student Hostel
Exterior plaster work in progress with doors/window frames being fixed.29_AMJ Ghana_Jamia Student Hostel
Main Facade30_AMJ Ghana_Jamia Student Hostel
Rear facade31_AMJ Ghana_Jamia Student Hostel
Aerial View Student Hostel Courtyard32_AMJ Ghana_Jamia Student Hostel
Student Hostel Courtyard33_AMJ Ghana_Jamia Student Hostel
Student Hostel Courtyard34_AMJ Ghana_Jamia Student Hostel
Internal Corridors35_AMJ Ghana_Jamia Student Hostel
Internal Corridors36_AMJ Ghana_Jamia Student Hostel
Typical Dormitory37_AMJ Ghana_Jamia Student Hostel
Washrooms
AMJ Tanzania National Jamaat Mission Development. Phase 2: Mosque Building
AMJ International Grant Funded Construction Projects
Project Name: AMJ Tanzania National Jamaat Mission Development. Phase 2: Mosque Building
Location: Dar es Salaam, Tanzania
Commenced: May 2017
Completed: December 2018
1_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Substructure work in progress2_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Building reinforced concrete column work in progress.3_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Ground floor and first floor structure complete.4_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Superstructure work complete up to second floor5_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Principle building structure works complete. Dome and minaret work in progress.6_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
External paintwork in progress.7_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Interior blockwork in progress.8_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Interior paintwork in progress.9_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Minaret and dome work progresses.10_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Internal finishes and fixtures work in progress.11_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Minaret ornamentation work in progress.12_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Interior picture of competed prayer area.13_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
View of completed mosque from within the mission compound.14_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Completed mosque project.
AMJ Tanzania National Jamaat Mission Development. Phase 1: Mission Building
AMJ International Grant Funded Construction Projects
Project Name: AMJ Tanzania National Jamaat Mission Development. Phase 1: Mission Building
Location: Dar es Salaam, Tanzania
Commenced: March 2016
Completed: April 2017
1_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Site clearance complete, excavation to commence.2_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Foundation reinforcement bar assembly.3_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Substructure complete, ground floor structural work commences.4_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Ground floor and first floor structural work.5_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Second floor reinforcement bar assembly.6_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Second floor structural work in progress.7_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Second floor structural work complete. Third floor structural work in progress.8_AMJ Tanzania_National Mission Development_Phase1_Mission Building
First floor blockwork in progress.9_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Ground floor ceiling plasterwork.10_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Fourth floor structural work in progress.11_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Fourth floor structural work in progress, fifth floor structural work commences.12_AMJ Tanzania_National Mission Development_Phase1_Mission Building
First floor stairwell blockwork in complete.13_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Fifth floor and roof terrace structure complete, façade, plasterwork and rendering in progress.14_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Stairwell skimming and painting in progress.15_AMJ Tanzania_National Mission Development_Phase1_Mission Building
First floor finishes and tilework in progress.16_AMJ Tanzania_National Mission Development_Phase1_Mission Building
WC tilework in progress.17_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Second floor corridor finishing in progress.18_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Third floor skimming in progress.19_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Fifth floor plasterwork in progress.20_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Roof terrace plasterwork façade rendering in progress.21_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Interior finishes and fixtures complete.22_AMJ Tanzania_National Mission Development_Phase1_Mission Building
External plasterwork complete.
BaitulAhad Mosque Conversion
AMJ International Grant Funded Construction Projects
Project Name: BaitulAhad Mosque Conversion
Location: Tsushima, Aichi, Japan
Commenced: 24 October 2014
Completed: 20 November 2015
1_AMJ Japan_BaitulAhad Mosque_Coversion
Original existing building.2_AMJ Japan_BaitulAhad Mosque_Coversion
Stripping of Interiors.3_AMJ Japan_BaitulAhad Mosque_Coversion
Stripping of Interiors.4_AMJ Japan_BaitulAhad Mosque_Coversion
Interior Renovation.5_AMJ Japan_BaitulAhad Mosque_Coversion
Interior Renovation.6_AMJ Japan_BaitulAhad Mosque_Coversion
Exterior Renovation.7_AMJ Japan_BaitulAhad Mosque_Coversion
Prefabricated Minaret.8_AMJ Japan_BaitulAhad Mosque_Coversion
Prefabricated Dome.9_AMJ Japan_BaitulAhad Mosque_Coversion
Exterior Works10_AMJ Japan_BaitulAhad Mosque_Coversion
Exterior Works11_AMJ Japan_BaitulAhad Mosque_Coversion
Exterior Works12_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Interiors17_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Project16_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Project15_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Project14_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Project13_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Project
Multi-function Hall and Hospitality suite, Basharat Mosque, Pedro-Abad, Spain
AMJ International Grant Funded Construction Projects
Project Name: Multi-function Hall and Hospitality suite
Location: Basharat Mosque, Pedro-Abad, Spain
Commenced: 4th August 2014
Completed: June 2016
1_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Structural works finished.4_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Roof frame-work commenced. Steel ridge beam and steal rafters were welded in place. Clay panels were placed in between the rafters5_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Props were removed at intervals.7_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Ground floor masonry work commenced.9_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Masonry work continued.12_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Interior masonry work continued13_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Interior masonry work complete14_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Exterior cement plaster work commenced18_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Building services work being carried out.19_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished roof tiling.20_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Interior surface finishing work being carried out.25_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished kitchen.26_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished multi-function hall.30_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished roof terrace.31_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished facade works.32_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished building front view.
Kampala Mosque Extension
AMJ International Grant Funded Construction Projects
Project Name: Kampala Mosque Extension
Location: Kampala, Uganda
Commenced: June 2011
Completed: July 2015
1_AMJ Intl_Uganda_Kampala Mosque Extention
Exterior Works.2_AMJ Intl_Uganda_Kampala Mosque Extention
Roof Ornament works.3_AMJ Intl_Uganda_Kampala Mosque Extention
Minaret Works.4_AMJ Intl_Uganda_Kampala Mosque Extention
Mosque and auxiliary building exterior renovation works.5_AMJ Intl_Uganda_Kampala Mosque Extention
Finished Mosque6_AMJ Intl_Uganda_Kampala Mosque Extention
Finished Mosque7_AMJ Intl_Uganda_Kampala Mosque Extention
Finished Mosque
Jamiat-ul Mubashireen Exisiting Student Hostel Rennovation
AMJ International Grant Funded Construction Projects
Project Name: Jamiat-ul Mubashireen Exisiting Student Hostel Rennovation
Location: Jamiat-ul Mubashireen, Eekrawfo, Ghana
Commenced: 28th March 2016
Completed: 1st July 2016
1_amj-ghana_jamia-mub_hostel-rennovation
Existing Student Hostel before Renovation2_amj-ghana_jamia-mub_hostel-rennovation
Existing Student Hostel before Renovation3_amj-ghana_jamia-mub_hostel-rennovation
Existing Student Hostel before Renovation4_amj-ghana_jamia-mub_hostel-rennovation
Timber frame roof upgrade in progress5_amj-ghana_jamia-mub_hostel-rennovation
Timber frame roof upgrade in progress6_amj-ghana_jamia-mub_hostel-rennovation
Aluminium roofing sheet upgrade in progress7_amj-ghana_jamia-mub_hostel-rennovation
Internal ceiling upgrade in progress.8_amj-ghana_jamia-mub_hostel-rennovation
Paintwork carried out.9_amj-ghana_jamia-mub_hostel-rennovation
Student Hostel after Renovation10_amj-ghana_jamia-mub_hostel-rennovation
Student Hostel after Renovation11_amj-ghana_jamia-mub_hostel-rennovation
Student Hostel after Renovation
Cotonou Mosque Extension
AMJ International Grant Funded Construction Projects
Project Name: Cotonou Mosque Extension
Location: Cotonou, Benin
Commenced: 25th February 2016
Completed: September 2016
1_amj-benin_cotonou-mosque-extention
Mosque before Construction.2_amj-benin_cotonou-mosque-extention
Dome and Minaret before construction.3_amj-benin_cotonou-mosque-extention
Demolition of dome4_amj-benin_cotonou-mosque-extention
Masonry work and columns casting in progress.5_amj-benin_cotonou-mosque-extention
Masonry and Beams casting work in progress.6_amj-benin_cotonou-mosque-extention
Window arcs being cast7_amj-benin_cotonou-mosque-extention
Roof slab being cast.8_amj-benin_cotonou-mosque-extention
Roof slab being cast.9_amj-benin_cotonou-mosque-extention
External tile work in progress10_amj-benin_cotonou-mosque-extention
Internal plasterwork in progress11_amj-benin_cotonou-mosque-extention
Minaret extension work in progress12_amj-benin_cotonou-mosque-extention
Internal finishes in progress.13_amj-benin_cotonou-mosque-extention
Finished minaret extension14_amj-benin_cotonou-mosque-extention
Finished interior15_amj-benin_cotonou-mosque-extention
Finished interior16_amj-benin_cotonou-mosque-extention
Finished balcony17_amj-benin_cotonou-mosque-extention
Finished extension front view18_amj-benin_cotonou-mosque-extention
Finished extension19_amj-benin_cotonou-mosque-extention
Finished extension
MTA International Broadcast Studio Ghana
AMJ International Grant Funded Construction Projects
Project Name: MTA International Broadcast Studio Ghana
Location: Accra, Ghana
Commenced: June 2015
Completed: October 2016
1_AMJ Ghana_MTA Studio
Casting of Foundations2_AMJ Ghana_MTA Studio
Block-work up to plinth level and Casting of ground Beam.3_AMJ Ghana_MTA Studio
Casting of columns4_AMJ Ghana_MTA Studio
Casting of columns5_AMJ Ghana_MTA Studio
Column and beams steal assembly.6_AMJ Ghana_MTA Studio
Casting of Beams.7_AMJ Ghana_MTA Studio
Casting of Beams.8_AMJ Ghana_MTA Studio
Casting of top Beams.9_AMJ Ghana_MTA Studio
Casting of top Beams.10_AMJ Ghana_MTA Studio
Casting of top Beams.11_AMJ Ghana_MTA Studio
Timber ‘form-work’ disassembled.12_AMJ Ghana_MTA Studio
Stair-case cast in place.13_AMJ Ghana_MTA Studio
‘Slab on grade’ floor concrete cast and studio area steel beams placed.14_AMJ Ghana_MTA Studio
MTA Ghana Studio front view.15_AMJ Ghana_MTA Studio
Masonry block-work commenced.16_AMJ Ghana_MTA Studio
Administration area masonry block-work complete.17_AMJ Ghana_MTA Studio
Administration area masonry block-work complete.18_AMJ Ghana_MTA Studio
Studio side ‘RCC’ roof slab cast in place.19_AMJ Ghana_MTA Studio
MTA Ghana Studio front view. Studio area masonry block-work in progress.20_AMJ Ghana_MTA Studio
Interior finishing in progress.21_AMJ Ghana_MTA Studio
Studio recording space.22_AMJ Ghana_MTA Studio
MTA Ghana Studio front view. Landscaping in progress.23_AMJ Ghana_MTA Studio
MTA Ghana Studio front view. Landscaping in progress.24_AMJ-Ghana_MTA-Studio.jpg
Broadcasting Studio Interior25_amj-ghana_mta-studio
Broadcasting Studio Interior26_amj-ghana_mta-studio
Control Room Interior27_amj-ghana_mta-studio
Reception Interior28_amj-ghana_mta-studio
MTA Ghana Studio Front View29_amj-ghana_mta-studio
MTA Ghana Studio Front View Night
Nusrat Jehan Mosque/Mission Extension
AMJ International Grant Funded Construction Projects
Project Name: Nusrat Jehan Mosque/Mission Extension
Location: Copenhagen, Denmark
Commenced: 29 June 2015
Completed: May 2016
1_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Nusrat Jehan Mosque Existing auxiliary building. (2 Eriksminde Alle)2_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Existing auxiliary was demolished. (2 Eriksminde Alle)3_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Existing residential Building. (22 Kirkegade Road)4_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Existing residential was demolished. (22 Kirkegade Road)5_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, building excavation, foundation and basement works carried out.6_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, building excavation, foundation and basement works carried out.7_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, basement and ground floor works.8_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, basement and ground floor works.9_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, ground floor block-work.10_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, ground floor block-work.11_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, brick veneer work.12_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, brick veneer work.13_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, Brick veneer and roof works complete.14_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, Brick veneer and roof works complete.15_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Building services work.16_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Building services work.17_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, Window fitting.18_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, Windows Fitted.19_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Interior finishing works.20_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Interior finishing fittings and fixtures.21_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Interior finishing fittings and fixtures.22_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Interior finishing fittings and fixtures.23_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Interior finishing fittings and fixtures.24_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, Exterior finish work.25_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, Partial Completion.26_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, Partial Completion.