Ongoing Projects
Ghana MTA Staff Apartments Project, Bustane-Ahmad
AMJ International Grant Funded Construction Projects
Project Name: Ghana MTA Staff Apartments Project, Bustane-Ahmad
Location: Bustane-Ahmad, Accra, Ghana
Commenced: 31st May 2021
-
1_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
Site mobilisation and setting out work complete. Excavation work in progress. -
2_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
Substructure masonry blockwork in progress: Pad and strip foundation work complete -
3_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
Substructure work complete. Ground floor slab concrete pour complete. -
4_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
Ground floor RCC column work and masonry block work in progress. -
5_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
Ground floor masonry blockwork complete. First floor RCC slab form work steel assembly in
progress. -
6_AMJ Ghana_MTA Staff Apartments Project_Bustane Ahmad
First Floor RCC slab concrete pour complete.
Philippines Central Mosque Construction Project
AMJ International Grant Funded Construction Projects
Project Name: Philippines Central Mosque Construction Project
Location: Zamboanga, Philippines
Commenced: 17th February 2021
-
1_AMJ Philippines_Central Mosque Construction Project_Zamboanga
Site mobilisation and setting out work complete. Excavation and substructure work in progress. -
2_AMJ Philippines_Central Mosque Construction Project_Zamboanga
Substructure work complete. Ground floor RCC column work in progress. -
3_AMJ Philippines_Central Mosque Construction Project_Zamboanga
Ground floor RCC column work complete. RCC beam and roof slab steel assembly work in
progress. -
4_AMJ Philippines_Central Mosque Construction Project_Zamboanga
RCC roof slab concrete pour complete. Masonry block work in progress. -
5_AMJ Philippines_Central Mosque Construction Project_Zamboanga
Masonry blockwork complete.
Chad Central Mosque & Mission Construction Project
AMJ International Grant Funded Construction Projects
Project Name: Chad Central Mosque & Mission Construction Project
Location: N’Djamena, Chad
Commenced: 16th September 2020
-
1_AMJ Chad_Central Mosque and Mission Construction Project
Site mobilisation and setting out work commences -
2_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building substructure work complete -
3_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building masonry blockwork in progress. -
4_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building masonry blockwork reached first floor level -
5_AMJ Chad_Central Mosque and Mission Construction Project
Missionary residence substructure work complete -
6_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building cement plasterwork in progress -
7_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building interior paintwork and first-fix electrical work in progress. -
8_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building phase 1 complete. View of main façade. -
9_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building phase 1 complete. View of side façade -
10_AMJ Chad_Central Mosque and Mission Construction Project
Mosque building phase 1 complete. Interior view of prayer hall. -
11_AMJ Chad_Central Mosque and Mission Construction Project
Missionary residence masonry blockwork in progress. -
12_AMJ Chad_Central Mosque and Mission Construction Project
Missionary residence masonry blockwork reaches roof level. -
13_AMJ Chad_Central Mosque and Mission Construction Project
Missionary residence rib & block roof slab concrete pour complete.
AMJ India, Continuous Development of Various Properties and sites, Progress through the year 2016
AMJ International Grant Funded Construction Projects
Project Name: AMJ India, Continuous Development of Various Properties and sites, Progress through the year 2016
Location: Various locations in India
Commenced: Continuous Development
-
1_AMJ India_Continuous Various Development
Construction of two flats, Mohallah Akalgarh, Qadian. -
2_AMJ India_Continuous Various Development
Construction of two flats, Interior, Mohallah Akalgarh, Qadian. -
3_AMJ India_Continuous Various Development
Construction of WC facilities, front view, Bahishti Maqbarah Cemetery, Qadian. -
4_AMJ India_Continuous Various Development
Construction of four flats, exterior view, Mohallah Ahmadiyya, Qadian. -
5_AMJ India_Continuous Various Development
Construction of four flats, typical interior, Mohallah Ahmadiyya, Qadian. -
6_AMJ India_Continuous Various Development
Construction of Khilafat Jubilee Monument, Bahishti Maqbarah Cemetery, Qadian. -
7_AMJ India_Continuous Various Development
Construction of Khilafat Jubilee Monument, night view, Bahishti Maqbarah Cemetery, Qadian. -
8_AMJ India_Continuous Various Development
Exterior lighting upgrade, Khilafat Jubilee Monument, Bahishti Maqbarah Cemetery, Qadian. -
9_AMJ India_Continuous Various Development
Pathway paving upgrade, Bahishti Maqbarah Cemetery, Qadian. -
10_AMJ India_Continuous Various Development
Renovation and Restoration of Masjid (Mosque) Aqsa New Portion, Qadian. -
11_AMJ India_Continuous Various Development
Renovation and Restoration of Masjid (Mosque) Aqsa Old Portion, Qadian. -
12_AMJ India_Continuous Various Development
Block 4 Construction, Six Flats, Kothi Darul Salam, Qadian. -
13_AMJ India_Continuous Various Development
Renovation of Taleem-ul-Islam High School Building, Qadian. -
14_AMJ India_Continuous Various Development
Renovation of Darul Bait Building, Ludhiana. -
15_AMJ India_Continuous Various Development
New-build Construction, Taleem-ul-Islam School Building, Qadian. -
16_AMJ India_Continuous Various Development
New Road Construction, Jalsa Gah Ground, Qadian. -
17_AMJ India_Continuous Various Development
New Road Construction, Jalsa Gah Ground, Qadian. -
18_AMJ India_Continuous Various Development
New-build Construction, Darul Ziafat Building, Qadian. -
19_AMJ India_Continuous Various Development
New-build Construction, Darul Ziafat Building, Qadian. External plasterwork and paintwork. -
20_AMJ India_Continuous Various Development
New-build Construction, Darul Ziafat Building, Qadian. External finishing work. -
21_AMJ India_Continuous Various Development
Renovation of Langar Khana (catering kitchen facility) No.1, Qadian. -
22_AMJ India_Continuous Various Development
Renovation of Langar Khana (catering kitchen facility) No.3, Qadian. External plasterwork. -
23_AMJ India_Continuous Various Development
Renovation of Langar Khana (catering kitchen facility) No.3, Qadian. Front view. -
24_AMJ India_Continuous Various Development
Renovation of Publications Warehouse (Nashro Ishaat), Qadian. -
25_AMJ India_Continuous Various Development
Marble restoration of the tomb of Hadhrat Mirza Ghulam Murtaza Sahib (rh) -
26_AMJ India_Continuous Various Development
New-build Construction, Police Quarters near Bahishti Maqbarah Cemetery, Qadian. -
27_AMJ India_Continuous Various Development
New-build Construction, Police Quarters near Darul Masih, Qadian. -
28_AMJ India_Continuous Various Development
Renovation of four storey block, Mohalla Ahmadiyya, Qadian. -
29_AMJ India_Continuous Various Development
New-build Construction, Darul Sanaat, Qadian. Exterior View. -
30_AMJ India_Continuous Various Development
New-build Construction, Darul Sanaat, Qadian. Interior. -
31_AMJ India_Continuous Various Development
Construction of WC facilities, Jalsa Gah, Qadian. Internal partition work. -
32_AMJ India_Continuous Various Development
Construction of WC facilities, Jalsa Gah, Qadian. Completed interior.
Finished Projects
Belize Central Mosque & Mission Construction Project
AMJ International Grant Funded Construction Projects
Project Name: Belize Central Mosque & Mission Construction Project
Location: Belize City, Belize
Commenced: 14th December 2019
Completed: 20th May 2021
-
1_AMJ Belize_Mosque and Mission Construction Project
Demolition of existing building and clearing land. -
2_AMJ Belize_Mosque and Mission Construction Project
Demolition of existing building complete. -
3_AMJ Belize_Mosque and Mission Construction Project
Foundation work commenced. Precast reinforced concrete piles driven into the ground -
4_AMJ Belize_Mosque and Mission Construction Project
Tie-beam and pile-caps form work and casting in progress. -
5_AMJ Belize_Mosque and Mission Construction Project
Tie-beam and pile-caps casting complete. Masonry block work in progress. -
6_AMJ Belize_Mosque and Mission Construction Project
Sub-structure work complete. Masonry block work reached plinth level. -
Project1_Belize_Mosque_Mission – 3D View – 3D View 1
3D View -
Elevation
-
7_AMJ Belize_Mosque and Mission Construction Project
Masonry block work in progress. -
8_AMJ Belize_Mosque and Mission Construction Project
Masonry block work reaches first floor level. -
9_AMJ Belize_Mosque and Mission Construction Project
Masonry block work complete. Roof slab concrete pour in progress. -
10_AMJ Belize_Mosque and Mission Construction Project
Superstructure complete. External ornamentation work in progress. -
11_AMJ Belize_Mosque and Mission Construction Project
External paintwork in progress. Dome and minarets installed. -
12_AMJ Belize_Mosque and Mission Construction Project
Mosque building complete. View from front façade. -
13_AMJ Belize_Mosque and Mission Construction Project
Mosque building complete. View from rear façade. -
14_AMJ Belize_Mosque and Mission Construction Project
Mosque building complete. Interior view of prayer hall. -
15_AMJ Belize_Mosque and Mission Construction Project
Mosque building complete. View from main road.
Macedonia New Mission Construction Project
AMJ International Grant Funded Construction Projects
Project Name: Macedonia New Mission Construction Project
Location: Pehchevo, Macedonia
Commenced: 20th February 2019
Status: Completed 30th October 2020
-
1_AMJ Macedonia_New Mission Construction Project
Jama`at land before construction. -
2_AMJ Macedonia_New Mission Construction Project
Foundation trenches excavated. -
3_AMJ Macedonia_New Mission Construction Project
Foundation concrete poured, reinforced concrete steal columns assembled and concrete cast up to first floor. -
4_AMJ Macedonia_New Mission Construction Project
Reinforced concrete structure work carried out to second floor. -
5_AMJ Macedonia_New Mission Construction Project
Reinforced concrete structure work carried out to roof level. External masonry block work is completed. Roof work is completed. -
6_AMJ Macedonia_New Mission Construction Project
Internal masonry block and first-fix electrical work complete. -
7_AMJ Macedonia_New Mission Construction Project
Internal plasterwork complete and windows fitted. -
8_AMJ Macedonia_New Mission Construction Project
Interior finishes work commences. -
9_AMJ Macedonia_New Mission Construction Project
Interior fixtures and fittings work in progress. -
10_AMJ Macedonia_New Mission Construction Project
All windows and doors fitted. -
11_AMJ Macedonia_New Mission Construction Project
Landscaping work commenced. Retaining wall construction in progress. -
12_AMJ Macedonia_New Mission Construction Project
Rear terrace retaining wall construction in progress. -
13_AMJ Macedonia_New Mission Construction Project
Building façade work in progress. Rear terrace retaining wall constructed. -
14_AMJ Macedonia_New Mission Construction Project
Building façade render work is complete. -
15_AMJ Macedonia_New Mission Construction Project
Principle view of finished building -
16_AMJ Macedonia_New Mission Construction Project
Rear view of finished building. -
17_AMJ Macedonia_New Mission Construction Project
Night time rear view of finished building. -
18_AMJ Macedonia_New Mission Construction Project
Principle façade entrance detail finished. -
19_AMJ Macedonia_New Mission Construction Project
Completed window pane details. -
20_AMJ Macedonia_New Mission Construction Project
Finished interior view of prayer area.
Guatemala Local Mosque & Mission Construction Project
AMJ International Grant Funded Construction Projects
Project Name: Guatemala Local Mosque & Mission Construction Project
Location: Cahabon, Guatemala
Commenced: 10th December 2019
Status: Completed 30th July 2020
-
1_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Site levelled and foundation trenches excavated. -
2_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Strip foundation concrete poured and plinth beam work in progress. -
3_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Ground floor masonry blockwork in progress. -
4_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
First floor reinforced concrete floor slab constructed. Frist floor masonry blockwork in progress. -
5_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Frist floor masonry blockwork reached roof level. -
6_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Reinforced concrete roof slab work complete. -
7_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Interior surface finishes and fixtures work progress. -
8_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
External plasterwork, minaret and site boundary wall construction in progress. -
9_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Minaret construction complete. White cement plaster work in progress -
10_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Principle view of completed mosque from road. -
11_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
View of completed mosque from rear. -
12_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Minaret with scenic backdrop -
13_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Finished main prayer hall interior. -
14_AMJ Guatemala_Cahabon Local Mosque and Mission Construction Project
Finished main prayer hall interior.
MSAF Islamabad Development Project. Phase 2: Residential Blocks
AMJ International Grant Funded Construction Projects
Project Name: MSAF Islamabad Development Project. Phase 2: Residential Blocks
Location: Tilford, Surrey, UK
Commenced: September 2017
Completed: April 2019
-
1_AMJ MSAF_Islamabad Development Project_Phase2
Demolition of existing buildings and clearing land. -
2_AMJ MSAF_Islamabad Development Project_Phase2
Land cleared. -
3_AMJ MSAF_Islamabad Development Project_Phase2
Foundation trenches excavated and strip foundation concrete being poured. -
4_AMJ MSAF_Islamabad Development Project_Phase2
Block 8 foundation work complete, ground floor block and beam floor work in progress. -
5_AMJ MSAF_Islamabad Development Project_Phase2
Masonry blockwork in progress. -
6_AMJ MSAF_Islamabad Development Project_Phase2
Masonry blockwork reaches first floor level. Floor joist work in progress. -
7_AMJ MSAF_Islamabad Development Project_Phase2
Masonry blockwork complete. Timber frame roof work in progress. -
8_AMJ MSAF_Islamabad Development Project_Phase2
Roof tile work in progress after installation of roof insulation and breather membrane. -
9_AMJ MSAF_Islamabad Development Project_Phase2
Building clad with composite panels resembling cedar wood. -
10_AMJ MSAF_Islamabad Development Project_Phase2
Completed residential blocks.
MSAF Islamabad Development Project. Phase 1: Mosque, Multi-Purpose Hall, Mix-use and Residential Blocks
AMJ International Grant Funded Construction Projects
Project Name: MSAF Islamabad Development Project. Phase 1: Mosque, Multi-Purpose Hall, Mix-use and Residential Blocks
Location: Tilford, Surrey, UK
Commenced: 24th October 2016
Completed: April 2019
-
1_AMJ MSAF_Islamabad Development Project_Phase1
Demolition of existing and clearing land. -
2_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall foundation work following excavation and land clearance work. -
3_AMJ MSAF_Islamabad Development Project_Phase1
Mosque foundation trench excavated and foundation stone set. -
4_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall foundation work. Concrete being poured for slab. -
5_AMJ MSAF_Islamabad Development Project_Phase1
Mosque foundation work. Concrete being poured for slab. -
6_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall steal erected. Mosque prep-work for reinforced concrete wall concrete pour. -
7_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block foundations trench excavated and concrete poured. -
8_AMJ MSAF_Islamabad Development Project_Phase1
Mosque reinforced concrete wall complete. Multi-purpose hall roof decking work in progress. -
9_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall roof decking complete. Super-structure masonry blockwork in progress. -
10_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ground floor slab concrete work pour complete, masonry brick-work in progress. -
11_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall brick veneer, breather membrane and roof substrate(organic and non-organic
material) work in progress. -
12_AMJ MSAF_Islamabad Development Project_Phase1
Mosque roof steelwork complete and installation of first GRP copper finish over timber
decking/sheathing and dampproof membrane. -
13_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘S’ beam and block floor work in-progress and steal portal frame assembled. -
14_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘1’ breather membrane installation after timber stud wall and timber roof joist
work complete. -
15_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall interior plaster skimming work, plant room installations, first-fix M&E work and
installation if windows. -
16_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘S’ external masonry leaf complete, interior masonry blockwork and timber roof
joist work in progress. -
17_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘1’ installation of slate roof tiles. -
18_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall first-fix MEP work in progress. -
19_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall first-fix MEP work, interior plasterwork, dampproof membrane and underfloor heating work in-progress. -
20_AMJ MSAF_Islamabad Development Project_Phase1
Mosque GRP copper finish panel installation continues. -
21_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Blocks first-fix MEP work along with the preparation of interior stud walls. -
22_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall first-fix MEP work continues. -
23_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall external timber cladding work commences. -
24_AMJ MSAF_Islamabad Development Project_Phase1
Mosque temporary interior steel work removed and first fix MEP work commences. -
25_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘1’ installation of external timber cladding. -
26_AMJ MSAF_Islamabad Development Project_Phase1
Mosque dome fixed in place. -
27_AMJ MSAF_Islamabad Development Project_Phase1
Mosque interior plasterboards installed following insulation and first-fix electrical installation. -
28_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall lighting installed and screeding complete. -
29_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall bathroom fixtures and finishing work in progress. -
30_AMJ MSAF_Islamabad Development Project_Phase1
Mosque dome pinnacle ornament fixed in place. -
31_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall hard landscaping work commences. -
32_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Blocks hard landscaping work commences. -
33_AMJ MSAF_Islamabad Development Project_Phase1
Mosque internal plasterwork continues. -
34_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Blocks interior finishing and light fixtures work in progress. -
35_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block 6 complete -
36_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block ‘S’ complete -
37_AMJ MSAF_Islamabad Development Project_Phase1
Mix-use Block 1 complete -
38_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall exterior view, complete -
39_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall interior, complete -
40_AMJ MSAF_Islamabad Development Project_Phase1
Multi-purpose hall washroom facilitates complete -
41_AMJ MSAF_Islamabad Development Project_Phase1
Mosque exterior view, complete -
42_AMJ MSAF_Islamabad Development Project_Phase1
Mosque interior view, complete
Archived Projects
AMJ Mali Central Mosque and Mission Project
AMJ International Grant Funded Construction Projects
Project Name: AMJ Mali Central Mosque and Mission Project
Location: Bamako, Mali
Commenced: March 2017
Completed: 2018
-
1_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mosque ground floor slab steel re-bar assembly in progress following completion of excavation and substructure work -
2_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mosque ground floor slab concrete pour complete. -
3_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Admin building substructure, ground floor structure and ground floor blockwork complete. First floor blockwork in progress. -
4_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mission building first floor reinforced concrete column and beam structure casting in progress. -
5_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mosque ground floor blockwork complete. Columns and beams concrete pour in progress. -
6_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mission building first floor structure work complete. -
7_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mission building superstructure work complete. -
8_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Prayer area plasterwork and first-fix works in progress. -
9_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mosque structural work complete up to first floor. -
10_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Mosque building superstructure work complete and minaret preparation in progress. -
11_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Completed prayer area. -
12_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Completed Mosque building. -
13_AMJ Mali_National Jamaat HQ Mosque and Mission Project
Completed Mosque and Jamaat Mission building
Jamia Ahmadiyya International, Student Hostels, Ghana
AMJ International Grant Funded Construction Projects
Project Name: Jamia Ahmadiyya International, Student Hostels
Location: Jamia Ahmadiyya International, Mankessim, Ghana
Commenced: 29th June 2015
Completed: 25th June 2016
-
1_AMJ Ghana_Jamia Student Hostel
Over 3000 sqm of land cleared. Building profile marked out. Foundation trenches excavated. -
2_AMJ Ghana_Jamia Student Hostel
Steel reinforcement pads and columns starters were placed. Foundation concrete was poured. -
3_AMJ Ghana_Jamia Student Hostel
Blocks were laid to up to plinth level. -
4_AMJ Ghana_Jamia Student Hostel
Excavation was back-filled. Super-structure work commenced. -
5_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ works -
6_AMJ Ghana_Jamia Student Hostel
Columns were cast and masonry block were laid up to roof level. -
7_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ works -
8_AMJ Ghana_Jamia Student Hostel
Casting of ‘Hostel A’ beam. -
9_AMJ Ghana_Jamia Student Hostel
Sanitary drainage pipes were laid for washrooms. -
10_AMJ Ghana_Jamia Student Hostel
Student Washrooms super-structure work and interior partition work commenced -
11_AMJ Ghana_Jamia Student Hostel
‘Hostel B’ works -
12_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ all columns and beams were cast and block-work finished up-to roof level. -
13_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ interior works. -
14_AMJ Ghana_Jamia Student Hostel
‘Hostel B’ works. -
15_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ timber frame roof works commenced. -
16_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ timber frame roof works. -
17_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ timber frame roof works. -
18_AMJ Ghana_Jamia Student Hostel
‘Hostel A’ timber frame roof works. -
19_AMJ Ghana_Jamia Student Hostel
-
20_AMJ Ghana_Jamia Student Hostel
Timber frame roof works Complete. -
21_AMJ Ghana_Jamia Student Hostel
Timber frame roof works Complete. -
22_AMJ Ghana_Jamia Student Hostel
Roofing metal sheets fixed. -
23_AMJ Ghana_Jamia Student Hostel
Roofing metal sheets fixed. -
24_AMJ Ghana_Jamia Student Hostel
Roofing metal sheet work complete. Damp-proof applied. -
25_AMJ Ghana_Jamia Student Hostel
Fine cement plaster work in progress with doors/window frames being fixed. -
26_AMJ Ghana_Jamia Student Hostel
Exterior plaster work in progress with doors/window frames being fixed. -
27_AMJ Ghana_Jamia Student Hostel
Exterior plaster work in progress with doors/window frames being fixed. -
28_AMJ Ghana_Jamia Student Hostel
Exterior plaster work in progress with doors/window frames being fixed. -
29_AMJ Ghana_Jamia Student Hostel
Main Facade -
30_AMJ Ghana_Jamia Student Hostel
Rear facade -
31_AMJ Ghana_Jamia Student Hostel
Aerial View Student Hostel Courtyard -
32_AMJ Ghana_Jamia Student Hostel
Student Hostel Courtyard -
33_AMJ Ghana_Jamia Student Hostel
Student Hostel Courtyard -
34_AMJ Ghana_Jamia Student Hostel
Internal Corridors -
35_AMJ Ghana_Jamia Student Hostel
Internal Corridors -
36_AMJ Ghana_Jamia Student Hostel
Typical Dormitory -
37_AMJ Ghana_Jamia Student Hostel
Washrooms
AMJ Tanzania National Jamaat Mission Development. Phase 2: Mosque Building
AMJ International Grant Funded Construction Projects
Project Name: AMJ Tanzania National Jamaat Mission Development. Phase 2: Mosque Building
Location: Dar es Salaam, Tanzania
Commenced: May 2017
Completed: December 2018
-
1_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Substructure work in progress -
2_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Building reinforced concrete column work in progress. -
3_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Ground floor and first floor structure complete. -
4_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Superstructure work complete up to second floor -
5_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Principle building structure works complete. Dome and minaret work in progress. -
6_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
External paintwork in progress. -
7_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Interior blockwork in progress. -
8_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Interior paintwork in progress. -
9_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Minaret and dome work progresses. -
10_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Internal finishes and fixtures work in progress. -
11_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Minaret ornamentation work in progress. -
12_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Interior picture of competed prayer area. -
13_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
View of completed mosque from within the mission compound. -
14_AMJ Tanzania_National Mission Development_Phase2_Mosque Building
Completed mosque project.
AMJ Tanzania National Jamaat Mission Development. Phase 1: Mission Building
AMJ International Grant Funded Construction Projects
Project Name: AMJ Tanzania National Jamaat Mission Development. Phase 1: Mission Building
Location: Dar es Salaam, Tanzania
Commenced: March 2016
Completed: April 2017
-
1_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Site clearance complete, excavation to commence. -
2_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Foundation reinforcement bar assembly. -
3_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Substructure complete, ground floor structural work commences. -
4_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Ground floor and first floor structural work. -
5_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Second floor reinforcement bar assembly. -
6_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Second floor structural work in progress. -
7_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Second floor structural work complete. Third floor structural work in progress. -
8_AMJ Tanzania_National Mission Development_Phase1_Mission Building
First floor blockwork in progress. -
9_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Ground floor ceiling plasterwork. -
10_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Fourth floor structural work in progress. -
11_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Fourth floor structural work in progress, fifth floor structural work commences. -
12_AMJ Tanzania_National Mission Development_Phase1_Mission Building
First floor stairwell blockwork in complete. -
13_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Fifth floor and roof terrace structure complete, façade, plasterwork and rendering in progress. -
14_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Stairwell skimming and painting in progress. -
15_AMJ Tanzania_National Mission Development_Phase1_Mission Building
First floor finishes and tilework in progress. -
16_AMJ Tanzania_National Mission Development_Phase1_Mission Building
WC tilework in progress. -
17_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Second floor corridor finishing in progress. -
18_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Third floor skimming in progress. -
19_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Fifth floor plasterwork in progress. -
20_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Roof terrace plasterwork façade rendering in progress. -
21_AMJ Tanzania_National Mission Development_Phase1_Mission Building
Interior finishes and fixtures complete. -
22_AMJ Tanzania_National Mission Development_Phase1_Mission Building
External plasterwork complete.
BaitulAhad Mosque Conversion
AMJ International Grant Funded Construction Projects
Project Name: BaitulAhad Mosque Conversion
Location: Tsushima, Aichi, Japan
Commenced: 24 October 2014
Completed: 20 November 2015
-
1_AMJ Japan_BaitulAhad Mosque_Coversion
Original existing building. -
2_AMJ Japan_BaitulAhad Mosque_Coversion
Stripping of Interiors. -
3_AMJ Japan_BaitulAhad Mosque_Coversion
Stripping of Interiors. -
4_AMJ Japan_BaitulAhad Mosque_Coversion
Interior Renovation. -
5_AMJ Japan_BaitulAhad Mosque_Coversion
Interior Renovation. -
6_AMJ Japan_BaitulAhad Mosque_Coversion
Exterior Renovation. -
7_AMJ Japan_BaitulAhad Mosque_Coversion
Prefabricated Minaret. -
8_AMJ Japan_BaitulAhad Mosque_Coversion
Prefabricated Dome. -
9_AMJ Japan_BaitulAhad Mosque_Coversion
Exterior Works -
10_AMJ Japan_BaitulAhad Mosque_Coversion
Exterior Works -
11_AMJ Japan_BaitulAhad Mosque_Coversion
Exterior Works -
12_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Interiors -
17_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Project -
16_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Project -
15_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Project -
14_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Project -
13_AMJ Japan_BaitulAhad Mosque_Coversion
Finished Project
Multi-function Hall and Hospitality suite, Basharat Mosque, Pedro-Abad, Spain
AMJ International Grant Funded Construction Projects
Project Name: Multi-function Hall and Hospitality suite
Location: Basharat Mosque, Pedro-Abad, Spain
Commenced: 4th August 2014
Completed: June 2016
-
1_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Structural works finished. -
4_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Roof frame-work commenced. Steel ridge beam and steal rafters were welded in place. Clay panels were placed in between the rafters -
5_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Props were removed at intervals. -
7_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Ground floor masonry work commenced. -
9_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Masonry work continued. -
12_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Interior masonry work continued -
13_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Interior masonry work complete -
14_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Exterior cement plaster work commenced -
18_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Building services work being carried out. -
19_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished roof tiling. -
20_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Interior surface finishing work being carried out. -
25_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished kitchen. -
26_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished multi-function hall. -
30_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished roof terrace. -
31_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished facade works. -
32_AMJ Spain_MultiPurpose Hall and Hospitality Suite
Finished building front view.
Kampala Mosque Extension
AMJ International Grant Funded Construction Projects
Project Name: Kampala Mosque Extension
Location: Kampala, Uganda
Commenced: June 2011
Completed: July 2015
-
1_AMJ Intl_Uganda_Kampala Mosque Extention
Exterior Works. -
2_AMJ Intl_Uganda_Kampala Mosque Extention
Roof Ornament works. -
3_AMJ Intl_Uganda_Kampala Mosque Extention
Minaret Works. -
4_AMJ Intl_Uganda_Kampala Mosque Extention
Mosque and auxiliary building exterior renovation works. -
5_AMJ Intl_Uganda_Kampala Mosque Extention
Finished Mosque -
6_AMJ Intl_Uganda_Kampala Mosque Extention
Finished Mosque -
7_AMJ Intl_Uganda_Kampala Mosque Extention
Finished Mosque
Jamiat-ul Mubashireen Exisiting Student Hostel Rennovation
AMJ International Grant Funded Construction Projects
Project Name: Jamiat-ul Mubashireen Exisiting Student Hostel Rennovation
Location: Jamiat-ul Mubashireen, Eekrawfo, Ghana
Commenced: 28th March 2016
Completed: 1st July 2016
-
1_amj-ghana_jamia-mub_hostel-rennovation
Existing Student Hostel before Renovation -
2_amj-ghana_jamia-mub_hostel-rennovation
Existing Student Hostel before Renovation -
3_amj-ghana_jamia-mub_hostel-rennovation
Existing Student Hostel before Renovation -
4_amj-ghana_jamia-mub_hostel-rennovation
Timber frame roof upgrade in progress -
5_amj-ghana_jamia-mub_hostel-rennovation
Timber frame roof upgrade in progress -
6_amj-ghana_jamia-mub_hostel-rennovation
Aluminium roofing sheet upgrade in progress -
7_amj-ghana_jamia-mub_hostel-rennovation
Internal ceiling upgrade in progress. -
8_amj-ghana_jamia-mub_hostel-rennovation
Paintwork carried out. -
9_amj-ghana_jamia-mub_hostel-rennovation
Student Hostel after Renovation -
10_amj-ghana_jamia-mub_hostel-rennovation
Student Hostel after Renovation -
11_amj-ghana_jamia-mub_hostel-rennovation
Student Hostel after Renovation
Cotonou Mosque Extension
AMJ International Grant Funded Construction Projects
Project Name: Cotonou Mosque Extension
Location: Cotonou, Benin
Commenced: 25th February 2016
Completed: September 2016
-
1_amj-benin_cotonou-mosque-extention
Mosque before Construction. -
2_amj-benin_cotonou-mosque-extention
Dome and Minaret before construction. -
3_amj-benin_cotonou-mosque-extention
Demolition of dome -
4_amj-benin_cotonou-mosque-extention
Masonry work and columns casting in progress. -
5_amj-benin_cotonou-mosque-extention
Masonry and Beams casting work in progress. -
6_amj-benin_cotonou-mosque-extention
Window arcs being cast -
7_amj-benin_cotonou-mosque-extention
Roof slab being cast. -
8_amj-benin_cotonou-mosque-extention
Roof slab being cast. -
9_amj-benin_cotonou-mosque-extention
External tile work in progress -
10_amj-benin_cotonou-mosque-extention
Internal plasterwork in progress -
11_amj-benin_cotonou-mosque-extention
Minaret extension work in progress -
12_amj-benin_cotonou-mosque-extention
Internal finishes in progress. -
13_amj-benin_cotonou-mosque-extention
Finished minaret extension -
14_amj-benin_cotonou-mosque-extention
Finished interior -
15_amj-benin_cotonou-mosque-extention
Finished interior -
16_amj-benin_cotonou-mosque-extention
Finished balcony -
17_amj-benin_cotonou-mosque-extention
Finished extension front view -
18_amj-benin_cotonou-mosque-extention
Finished extension -
19_amj-benin_cotonou-mosque-extention
Finished extension
MTA International Broadcast Studio Ghana
AMJ International Grant Funded Construction Projects
Project Name: MTA International Broadcast Studio Ghana
Location: Accra, Ghana
Commenced: June 2015
Completed: October 2016
-
1_AMJ Ghana_MTA Studio
Casting of Foundations -
2_AMJ Ghana_MTA Studio
Block-work up to plinth level and Casting of ground Beam. -
3_AMJ Ghana_MTA Studio
Casting of columns -
4_AMJ Ghana_MTA Studio
Casting of columns -
5_AMJ Ghana_MTA Studio
Column and beams steal assembly. -
6_AMJ Ghana_MTA Studio
Casting of Beams. -
7_AMJ Ghana_MTA Studio
Casting of Beams. -
8_AMJ Ghana_MTA Studio
Casting of top Beams. -
9_AMJ Ghana_MTA Studio
Casting of top Beams. -
10_AMJ Ghana_MTA Studio
Casting of top Beams. -
11_AMJ Ghana_MTA Studio
Timber ‘form-work’ disassembled. -
12_AMJ Ghana_MTA Studio
Stair-case cast in place. -
13_AMJ Ghana_MTA Studio
‘Slab on grade’ floor concrete cast and studio area steel beams placed. -
14_AMJ Ghana_MTA Studio
MTA Ghana Studio front view. -
15_AMJ Ghana_MTA Studio
Masonry block-work commenced. -
16_AMJ Ghana_MTA Studio
Administration area masonry block-work complete. -
17_AMJ Ghana_MTA Studio
Administration area masonry block-work complete. -
18_AMJ Ghana_MTA Studio
Studio side ‘RCC’ roof slab cast in place. -
19_AMJ Ghana_MTA Studio
MTA Ghana Studio front view. Studio area masonry block-work in progress. -
20_AMJ Ghana_MTA Studio
Interior finishing in progress. -
21_AMJ Ghana_MTA Studio
Studio recording space. -
22_AMJ Ghana_MTA Studio
MTA Ghana Studio front view. Landscaping in progress. -
23_AMJ Ghana_MTA Studio
MTA Ghana Studio front view. Landscaping in progress. -
24_AMJ-Ghana_MTA-Studio.jpg
Broadcasting Studio Interior -
25_amj-ghana_mta-studio
Broadcasting Studio Interior -
26_amj-ghana_mta-studio
Control Room Interior -
27_amj-ghana_mta-studio
Reception Interior -
28_amj-ghana_mta-studio
MTA Ghana Studio Front View -
29_amj-ghana_mta-studio
MTA Ghana Studio Front View Night
Nusrat Jehan Mosque/Mission Extension
AMJ International Grant Funded Construction Projects
Project Name: Nusrat Jehan Mosque/Mission Extension
Location: Copenhagen, Denmark
Commenced: 29 June 2015
Completed: May 2016
-
1_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Nusrat Jehan Mosque Existing auxiliary building. (2 Eriksminde Alle) -
2_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Existing auxiliary was demolished. (2 Eriksminde Alle) -
3_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Existing residential Building. (22 Kirkegade Road) -
4_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Existing residential was demolished. (22 Kirkegade Road) -
5_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, building excavation, foundation and basement works carried out. -
6_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, building excavation, foundation and basement works carried out. -
7_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, basement and ground floor works. -
8_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, basement and ground floor works. -
9_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, ground floor block-work. -
10_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, ground floor block-work. -
11_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, brick veneer work. -
12_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, brick veneer work. -
13_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, Brick veneer and roof works complete. -
14_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, Brick veneer and roof works complete. -
15_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Building services work. -
16_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Building services work. -
17_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, Window fitting. -
18_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
22 Kirkegade Road, Windows Fitted. -
19_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Interior finishing works. -
20_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Interior finishing fittings and fixtures. -
21_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Interior finishing fittings and fixtures. -
22_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Interior finishing fittings and fixtures. -
23_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
Interior finishing fittings and fixtures. -
24_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, Exterior finish work. -
25_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, Partial Completion. -
26_AMJ Denmark_Nusrat Jehan Mosque_Mission Extension.
2 Eriksminde Alle, Partial Completion.